Page 1 of 13
EXAM CONSTRUCTION TECHNOLOGIES
AND MANAGEMENT III
Task 1: Construction methods and work
preparation (90 min)
Surname, first name: .................................................
Matriculation number .................................................
Please note the following:
Please place your student ID and photo ID in the free space to your right.
The tasks are to be stapled and handed in separately. Therefore, use a new sheet
for each task.
Missing information shall be reasonably assumed and justified from a construction
point of view.
After the end of the processing time, you will place your exam on the table. The
exams will then be collected by the supervising staff. Please remain seated until
you are asked to leave the room.
We wish you all the best for the exam!
Institut für Baubetrieb
Institute of Construction
Technologies and Management
Univ.-Prof. Dr.-Ing. Christoph Motzko
Dr.-Ing. Jörg Fenner
Date:
25 2023
Name: ................................................................. Matr.-No.: ............................
Task 1: Construction methods and work preparation
You work for a construction company and support the work preparation for the construc-
tion of a 1,000-meter-long reinforced concrete canal. Your tasks include earthworks,
sealing works and the construction of the reinforced concrete structure (ref. Figure 1-
for top view and Figure 1-2 for vertical section).
Figure 1-1: Top view takt section canal
Name: ................................................................. Matr.-No.: ............................
c) Work estimate (30 min.)
You are at the time of the beginning of the construction works. For the controlling
of the construction project, a comprehensible work estimation has to be estab-
lished under consideration of the given boundary conditions. It was decided to
subcontract the reinforcement works for the canal bottom slab and the canal walls.
Use annex 1-3 to prepare the work estimation. In addition, calculate the contribu-
tion margin, the construction site result and the contract amount.
Below quantities refer to one (1) kilometre (1,000 m) of canal
Quantities earthworks (rounded):
Excavation works = 32,000 m³
Quantities blinding concrete (rounded):
Concrete volume blinding concrete = 2,250 m³
Performance casting (includes set-up time) = 0 h/m³
Quantities sealing sheet (rounded):
Total surface sealing sheet = 13,000 m²
Performance sealing works (includes set-up time) = 0 h/m²
Quantities canal bottom slab (rounded):
Concrete volume bottom slab = 1,500 m³
Reinforcement content bottom slab = 110 kg/m³ concrete
Performance steel-fixing (includes set-up time) = 16 h/t
Performance casting (includes set-up time) = 0 h/m³
Quantities canal walls (rounded):
Surface area canal walls = 9,000 m²
Concrete volume canal walls = 1,750 m³
Reinforcement content canal walls = 120 kg/m³ concrete
Performance shuttering (includes set-up time) = 0 h/m²
Performance stripping (includes set-up time) = 0 h/m²
Performance steel-fixing (includes set-up time) = 14 h/t
Performance casting (includes set-up time) = 0 h/m³
Name: ................................................................. Matr.-No.: ............................
General boundary conditions:
- The awarded scope of works comprises the earthworks, the sealing works and the
reinforced concrete works of the canal.
- No influences from the surroundings of the canal have to be taken into account.
- The specification of construction joints between the sections are yet to be agreed
with the structural engineer and are not part of this task.
- Soil condition: Soil classification 4 according to DIN 18300:2012-09.
- The slope can be assumed to be sufficiently stable.
- All concrete components are made of concrete grade C30/37.
- A truck-mounted concrete pump is planned for the casting process.
Figure 1-3: Digging curve hydraulic excavator
Name: ................................................................. Matr.-No.: ............................
Labour cost:
- Wage rate ASL: 45 €/h
- Wage-related cost: 98 %
Turnover-related overheads (related to total bid amount):
- Own performance:
General business overhead 8 %, Interest for advance performances 4 %,
General business risk 3 %, Profit 1 %
- Subcontractor performance:
General business overhead 6 %, Interest for advance performances 4 %,
General business risk 2 %, Profit 1 %
Material Cost:
- Concrete grade C30/37 free site: 160 €/m³
- Lean concrete for blinding layer free site: 110 €/m³
- Sealing sheet free site: 10 €/m²
Equipment Cost:
- Formwork canal walls free site:
- Rental rate: 12 €/(m² x month)
- Quantity formwork for operation: 400 m²
- Equipment cost of one hydraulic excavator:
- Operating time hydraulic excavator 40 h/week
- Productive output QA : 65 m³/h
- Engine Power: 100 kW
- Fuel consumption: 0 l/kWh
- Fuel cost: 1 €/l
- Equpiment new value: 201,000 €
- Years of use: 8
- Operating months: 80
- Imputed interest rate: 6 %
- Monthly repair rate (BGL): 1 %
- The lubricant cost are 20 % of the fuel cost.
Name: ................................................................. Matr.-No.: ............................
Subcontractor cost:
- Delivery and removal of one hydraulic excavator each: 5,000 €
- Removal and dumping cost excavated material: 10 €/m³
- Providing and fixing reinforcement (Material and wage)
- Components reinforcement content 110 kg/m³: 1,500 €/t
- Components reinforcement content 120 kg/m³: 1,600 €/t
Salaries:
- Site manager: 12,000 €/month
- Foreman: 8,000 €/month
On-Site overhead:
- Technical design: 500 h
- Cleaning of the construction site: 4,000 €
- Wage hours for auxiliary works: 1,000 h
- Construction site installation: 10,000 €/month
Missing parameters shall be reasonably assumed and justified from a construction
point of view.
XX XX XX XX XX XX
####### Working Days
####### Activity 1 2 Week n 3 4 5 6 7 Week n+1 8 9 10 11 12 Week n+2 13 14 15 16 17 Week n+3 18 19 2021 22 Week n+4 23 24 25 26 27 Week n+5 28 29 30 3132 Week n+6 33 34
Name: .............................................................. Matr.-No.: .........................................................
Annex 1-
Page 10 of 13
Name: ................................................................. Matr.-No.: ............................
Annex 1-3:
Name: ................................................................. Matr.-No.: ............................
Page 1 of 7
EXAM CONSTRUCTION TECHNOLOGIES
AND MANAGEMENT III
Task 2: Construction contract law (30 min)
Surname, first name: .................................................
Matriculation number: .................................................
Please note the following:
Please place your student ID and photo ID in the free space to your right.
The tasks are to be stapled and handed in separately. Therefore, use a new sheet
for each task.
Missing information shall be reasonably assumed and justified from a construction
point of view.
After the end of the processing time, you will place your exam on the table. The
exams will then be collected by the supervising staff. Please remain seated until
you are asked to leave the room.
We wish you all the best for the exam!
Institut für Baubetrieb
Institute of Construction
Technologies and Management
Univ.-Prof. Dr.-Ing. Christoph Motzko
Dr.-Ing. Jörg Fenner
Date:
25 2023
Name: ................................................................. Matr.-No.: ............................
c) General terms and conditions are part of consumer protection. What are relevant
statutory provisions regarding general terms and conditions? (2 minutes)
d) What are the effects of acceptance? (3 minutes)
Name: ................................................................. Matr.-No.: ............................
e) What options are there for the contractor to terminate a VOB/B contract?
(4 minutes)
f) What are the effects of default according to VOB/B? (2 minutes)
Name: ................................................................. Matr.-No.: ............................
i) Is the employer obliged to render a partial acceptance to the planer? Describe the
previous and new legal situation. (3 minutes)
j) Name the two remuneration models of the HOAI. What are their basic differences?
(4 minutes)
Name: ................................................................. Matr.-No.: ............................
k) What is FIDIC? (3 minutes)
l) Why using a FIDIC contract? (2 minutes)
War dieses Dokument hilfreich?
CTM3-So Se23-Klausur - Exam CTMIII SoSe2023
Kurs: Baubetrieb B1 (13-A0-M001)
29 Dokumente
Studierenden haben 29 Dokumente in diesem Kurs geteilt
Universität: Technische Universität Darmstadt
War dieses Dokument hilfreich?
Page 1 of 13
EXAM CONSTRUCTION TECHNOLOGIES
AND MANAGEMENT III
Task 1: Construction methods and work
preparation (90 min)
Surname, first name: .................................................
Matriculation number .................................................
Please note the following:
Please place your student ID and photo ID in the free space to your right.
The tasks are to be stapled and handed in separately. Therefore, use a new sheet
for each task.
Missing information shall be reasonably assumed and justified from a construction
point of view.
After the end of the processing time, you will place your exam on the table. The
exams will then be collected by the supervising staff. Please remain seated until
you are asked to leave the room.
We wish you all the best for the exam!
Institut für Baubetrieb
Institute of Construction
Technologies and Management
Univ.-Prof. Dr.-Ing. Christoph Motzko
Dr.-Ing. Jörg Fenner
Date:
25.August 2023
Exam Construction Technologies and Management III Summer semester 2023
Name: ……………………………………………….………. Matr.-No.: ….……………………
Task 1 Page 2 of 13
Task 1: Construction methods and work preparation
You work for a construction company and support the work preparation for the construc-
tion of a 1,000-meter-long reinforced concrete canal. Your tasks include earthworks,
sealing works and the construction of the reinforced concrete structure (ref. Figure 1-1
for top view and Figure 1-2 for vertical section).
Figure 1-1: Top view takt section canal
Exam Construction Technologies and Management III Summer semester 2023
Name: ……………………………………………….………. Matr.-No.: ….……………………
Task 1 Page 3 of 13
Figure 1-2: Vertical section canal (Section A-A)
Tasks:
a) Construction Method (35 min.)
Establish an excavation concept and prove it with the help of hand sketches. Con-
sider the digging curve of the hydraulic excavator shown in Figure 1-3. In addi-
tion, describe all work processes for the construction of the canal and prepare
informative hand sketches for the reinforced concrete works. Develop a crane con-
cept for the reinforced concrete works and draw a hand sketch.
b) Takt scheduling (25 min.)
Develop a takt schedule for the structural construction works of the canal. Use the
template in annex 1-1 for the bill of quantities and the template in annex 1-2 for
the takt schedule. Show at least three (3) takts. Calculate the minimum number
of formwork sets required for the construction of the canal walls and draw them
in the takt schedule.
Zu lang zum Lesen auf dem Handy? Speichere es zum späteren Lesen auf deinem Computer
Exam Construction Technologies and Management III Summer semester 2023
Name: ……………………………………………….………. Matr.-No.: ….……………………
Task 1 Page 4 of 13
c) Work estimate (30 min.)
You are at the time of the beginning of the construction works. For the controlling
of the construction project, a comprehensible work estimation has to be estab-
lished under consideration of the given boundary conditions. It was decided to
subcontract the reinforcement works for the canal bottom slab and the canal walls.
Use annex 1-3 to prepare the work estimation. In addition, calculate the contribu-
tion margin, the construction site result and the contract amount.
Below quantities refer to one (1) kilometre (1,000 m) of canal
Quantities earthworks (rounded):
Excavation works = 32,000 m³
Quantities blinding concrete (rounded):
Concrete volume blinding concrete = 2,250 m³
Performance casting (includes set-up time) = 0.35 h/m³
Quantities sealing sheet (rounded):
Total surface sealing sheet = 13,000 m²
Performance sealing works (includes set-up time) = 0.12 h/m²
Quantities canal bottom slab (rounded):
Concrete volume bottom slab = 1,500 m³
Reinforcement content bottom slab = 110 kg/m³ concrete
Performance steel-fixing (includes set-up time) = 16.00 h/t
Performance casting (includes set-up time) = 0.50 h/m³
Quantities canal walls (rounded):
Surface area canal walls = 9,000 m²
Concrete volume canal walls = 1,750 m³
Reinforcement content canal walls = 120 kg/m³ concrete
Performance shuttering (includes set-up time) = 0.25 h/m²
Performance stripping (includes set-up time) = 0.15 h/m²
Performance steel-fixing (includes set-up time) = 14.00 h/t
Performance casting (includes set-up time) = 0.45 h/m³
Exam Construction Technologies and Management III Summer semester 2023
Name: ……………………………………………….………. Matr.-No.: ….……………………
Task 1 Page 5 of 13
General boundary conditions:
• The awarded scope of works comprises the earthworks, the sealing works and the
reinforced concrete works of the canal.
• No influences from the surroundings of the canal have to be taken into account.
• The specification of construction joints between the sections are yet to be agreed
with the structural engineer and are not part of this task.
• Soil condition: Soil classification 4 according to DIN 18300:2012-09.
• The slope can be assumed to be sufficiently stable.
• All concrete components are made of concrete grade C30/37.
• A truck-mounted concrete pump is planned for the casting process.
Figure 1-3: Digging curve hydraulic excavator
Exam Construction Technologies and Management III Summer semester 2023
Name: ……………………………………………….………. Matr.-No.: ….……………………
Task 1 Page 6 of 13
Boundary conditions task b):
• The earthworks are to be neglected in the course of the takt scheduling and
run independently.
• The 1,000-meter-long canal is to be completed after 260 working days.
• The length of each takt section of the canal is 20 meters.
• A learning curve is not to consider.
• The formwork and concrete works will be carried out by your own working crew
(Crew A). The working crew works from Monday to Friday. The weekly working
time is 40 hours.
• Your own work crew (Crew A) also carries out the construction of the blinding
concrete and placing the sealing sheets.
• The placing of the sealing sheet happens immediately after casting of the blinding
concrete.
• Works on the canal bottom slab may begin no earlier than 2 calendar days after
the concrete is casted. The stripping period for the canal walls is 9 calendar days.
• The reinforcement works of the canal bottom slab and canal walls are carried out
by another work crew (Crew B). This work crew will also carry out the shuttering
of the canal bottom slab. The shuttering works of the canal bottom slab is not to
be considered further. Work crew B is employed on the construction site 4 work-
ing days per week. The weekly working time is 40 hours.
• The reinforcement works for the canal bottom slab can first start half a working
day after the start of the sealing sheet works.
Boundary conditions task c):
General boundary conditions:
• The working time is 40 hours a week per worker.
• The total construction period is 16 months.
• The earthworks are to be included in the estimation.
• The construction manager is assigned 50 % to the project.
• There are two foremen assigned to the site. The foremen do not work productively
on the site.
• The formwork is delivered one month after the start of the construction works and
carted off one month before the end of the construction works. The formwork is
rental material.
Entdecke mehr von:
- Entdecke mehr von:
Exam Construction Technologies and Management III Summer semester 2023
Name: ……………………………………………….………. Matr.-No.: ….……………………
Task 1 Page 7 of 13
Labour cost:
• Wage rate ASL: 45.00 €/h
• Wage-related cost: 98 %
Turnover-related overheads (related to total bid amount):
• Own performance:
General business overhead 8 %, Interest for advance performances 4 %,
General business risk 3 %, Profit 1 %
• Subcontractor performance:
General business overhead 6 %, Interest for advance performances 4 %,
General business risk 2 %, Profit 1 %
Material Cost:
• Concrete grade C30/37 free site: 160.00 €/m³
• Lean concrete for blinding layer free site: 110.00 €/m³
• Sealing sheet free site: 10.00 €/m²
Equipment Cost:
• Formwork canal walls free site:
• Rental rate: 12.00 €/(m² x month)
• Quantity formwork for operation: 400 m²
• Equipment cost of one hydraulic excavator:
• Operating time hydraulic excavator 40 h/week
• Productive output QA: 65 m³/h
• Engine Power: 100 kW
• Fuel consumption: 0.2 l/kWh
• Fuel cost: 1.70 €/l
• Equpiment new value: 201,000.00 €
• Years of use: 8
• Operating months: 80
• Imputed interest rate: 6.5 %
• Monthly repair rate (BGL): 1.6 %
• The lubricant cost are 20 % of the fuel cost.
Exam Construction Technologies and Management III Summer semester 2023
Name: ……………………………………………….………. Matr.-No.: ….……………………
Task 1 Page 8 of 13
Subcontractor cost:
• Delivery and removal of one hydraulic excavator each: 5,000.00 €
• Removal and dumping cost excavated material: 10.00 €/m³
• Providing and fixing reinforcement (Material and wage)
• Components reinforcement content 110 kg/m³: 1,500.00 €/t
• Components reinforcement content 120 kg/m³: 1,600.00 €/t
Salaries:
• Site manager: 12,000.00 €/month
• Foreman: 8,000.00 €/month
On-Site overhead:
• Technical design: 500 h
• Cleaning of the construction site: 4,000.00 €
• Wage hours for auxiliary works: 1,000 h
• Construction site installation: 10,000.00 €/month
Missing parameters shall be reasonably assumed and justified from a construction
point of view.
Exam Construction Technologies and Management III
Summer semester 2023
Quantity per takt section Unit Process
Performance
factor [h/Unit]
Hours Workers
Durations
[Days]
Name: ..............................................................Matr.-No.: .........................................................
Annex 1-1
Page 9 of 13
Exam Construction Technologies and Management III Summer semester 2023
X
X
X
X
X
X
X
X
X
X
X
X
Working Days
Activity
1
2
3
4
5
6
7
8
20
9
10
11
12
13
14
15
16
17
18
19
32
21
22
23
24
25
26
27
28
29
30
31
Week n
Week n+1
Week n+2
Week n+3
Week n+4
Week n+5
Week n+6
33
34
35
Name: .............................................................. Matr.-No.: .........................................................
Annex 1-2
Page 10 of 13