| CE 30/2023 (CE) |
Term Consultancy for Site Formation and Infrastructure Works for Proposed Housing and Other Developments in Zone 4 (2023-2027) - Feasibility Study |
AECOM Asia Company Limited |
21/09/2023 |
21/09/2023 |
20/09/2027 |
HK$38,217,380.00 |
| CE 29/2023 (CE) |
Term Consultancy for Site Formation and Infrastructure Works for Proposed Housing and Other Developments in Zone 3 (2023-2027) - Feasibility Study |
Atkins China Limited |
21/09/2023 |
21/09/2023 |
20/09/2027 |
HK$39,627,500.00 |
| CE 37/2023 (CE) |
Site Formation and Infrastructure Works for Public Housing Development at Wa Shan, Sheung Shui – Investigation, Design and Construction |
Atkins China Limited |
12/09/2023 |
12/09/2023 |
11/01/2034 |
HK$13,800,000.00 |
| CE 39/2023 (CE) |
Study on Topside Development above Exhibition Centre Station – Feasibility Study |
Ove Arup and Partners Hong Kong Limited |
28/08/2023 |
30/08/2023 |
30/08/2025 |
HK$19,888,000.00 |
| CE 20/2023 (CE) |
Term Consultancy for Site Formation and Infrastructure Works for Proposed Housing and Other Developments in Zone 2 (2023-2027) - Feasibility Study |
Atkins China Limited |
15/08/2023 |
15/08/2023 |
14/08/2027 |
HK$38,198,750.00 |
| CE 19/2023 (CE) |
Term Consultancy for Site Formation and Infrastructure Works for Proposed Housing and Other Developments in Zone 1 (2023-2027) - Feasibility Study |
Mott MacDonald Hong Kong Limited |
15/08/2023 |
15/08/2023 |
14/08/2027 |
HK$29,645,400.00 |
| CE 32/2023 (CE) |
Relocation of Western Harbour Crossing Administration Building – Investigation, Design and Construction |
WSP (Asia) Limited |
07/08/2023 |
10/08/2023 |
09/02/2030 |
HK$39,800,000.00 |
| CE 14/2023 (GE) |
Management and Operation of Public Works Regional Laboratory (Kowloon) – Design and Construction |
Fugro (Hong Kong) Limited |
19/07/2023 |
21/07/2023 |
20/09/2027 |
HK$23,309,000.00 |
| CE 13/2023 (GE) |
Management and Operation of Public Works Regional Laboratory (North Lantau) – Design and Construction |
C M Wong & Associates Limited |
19/07/2023 |
21/07/2023 |
20/09/2027 |
HK$28,140,000.00 |
| CE 85/2022(CE) |
Improvement Works at Tap Mun Pier - Feasibility Study, Investigation, Design & Construction |
Ove Arup & Partners Hong Kong Limited |
19/07/2023 |
02/08/2023 |
01/03/2029 |
HK$8,996,000.00 |
| CE53/2022(GE) |
Landslip Prevention and Mitigation Programme, 2022, Package G, Landslip Prevention and Mitigation Works – Investigation, Design and Construction |
AECOM Asia Company Limited |
13/06/2023 |
10/07/2023 |
09/07/2029 |
HK$19,500,000.00 |
| CE 6/2023 (CE) |
Study for Developments of Tuen Mun East and Adjacent Green Belt Cluster – Feasibility Study |
Ove Arup & Partners Hong Kong Limited |
05/05/2023 |
10/05/2023 |
09/11/2025 |
HK$41,793,000.00 |
| CE 4/2023 (CE) |
Round-the-Island Trail on Hong Kong Island - Feasibility Study |
WSP (Asia) Limited |
04/05/2023 |
08/05/2023 |
07/05/2025 |
HK$13,800,000.00 |
| CE 5/2023 (CE) |
Engineering Study on Sunny Bay Reclamation – Feasibility Study |
Ove Arup & Partners Hong Kong Limited |
28/04/2023 |
02/05/2023 |
01/05/2025 |
HK$15,200,000.00 |
| CE 86/2022 (GE) |
Regional Geological Study of Northern New Territories (North) – Feasibility Study |
AECOM Asia Company Limited |
06/04/2023 |
12/04/2023 |
11/04/2027 |
HK$15,504,000.00 |
| CE 87/2022 (GE) |
Regional Geological Study of Northern New Territories (Northwest) – Feasibility Study |
Ove Arup & Partners Hong Kong Limited |
06/04/2023 |
12/04/2023 |
11/04/2027 |
HK$14,888,000.00 |